[[Maintenance (glossary)|System Maintenance]] planning begins early in the acquisition process with development of a maintenance concept. Maintenance planning is conducted to evolve and establish requirements and tasks to be accomplished for achieving, restoring, and maintaining operational capability for the life of the system. For a [[System (glossary)|system]] to be sustained throughout its [[Life Cycle (glossary)|system life cycle]], the maintenance process has to be executed concurrently with the operations process ([[ISO/IEC/IEEE 15288]]:2008, Clause 6.4.9).
+
[[Maintenance (glossary)|System Maintenance]] planning begins early in the acquisition process with development of a maintenance concept. Maintenance planning is conducted to evolve and establish requirements and tasks to be accomplished for achieving, restoring, and maintaining operational capability for the life of the system. For a [[System (glossary)|system]] to be sustained throughout its [[Life Cycle (glossary)|system life cycle]], the maintenance process has to be executed concurrently with the operations process ([[ISO/IEC/IEEE 15288]]:2015, Clause 6.4.9).
  
 
==Overview==
 
==Overview==
The initial requirements for maintenance have to be defined during the [[Stakeholder Needs and Requirements|stakeholder’s requirement definition process]] (Clause 6.4.1) ([[ISO/IEC/IEEE 15288]]:2008) and continue to evolve during the operation of the system. Considerations include
+
The initial requirements for maintenance have to be defined during the [[Stakeholder Needs and Requirements|stakeholder’s requirement definition process]] (Clause 6.4.1) ([[ISO/IEC/IEEE 15288]]:2015) and continue to evolve during the operation of the system. Considerations include
  
 
* Maximizing system availability to meet the operational requirements. This has to take into account the designed-in [[Reliability (glossary)|reliability]] and [[Maintainability (glossary)|maintainability]] of the system and resources available.
 
* Maximizing system availability to meet the operational requirements. This has to take into account the designed-in [[Reliability (glossary)|reliability]] and [[Maintainability (glossary)|maintainability]] of the system and resources available.
Line 49: Line 49:
  
 
===Works Cited===
 
===Works Cited===
ISO/IEC/IEEE. 2008. ''[[ISO/IEC/IEEE 15288|Systems and Software Engineering - System Life Cycle Processes]].'' Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineers. [[ISO/IEC/IEEE 15288]]:2008 (E).
+
ISO/IEC/IEEE. 2015.''[[ISO/IEC/IEEE 15288|Systems and Software Engineering - System Life Cycle Processes]].''Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineers.[[ISO/IEC/IEEE 15288]]:2015.
  
 
===Primary References===
 
===Primary References===
Line 60: Line 60:
 
Institute of Engineers Singapore. 2009. ''[[Systems Engineering Body of Knowledge (Singapore)|Systems Engineering Body of Knowledge]],'' Provisional version 2.0. Singapore: Institute of Engineers Singapore.
 
Institute of Engineers Singapore. 2009. ''[[Systems Engineering Body of Knowledge (Singapore)|Systems Engineering Body of Knowledge]],'' Provisional version 2.0. Singapore: Institute of Engineers Singapore.
  
ISO/IEC/IEEE. 2008. ''[[ISO/IEC/IEEE 15288|Systems and Software Engineering - System Life Cycle Processes]].'' Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineers. [[ISO/IEC/IEEE 15288]]:2008 (E).
+
IISO/IEC/IEEE. 2015.''[[ISO/IEC/IEEE 15288|Systems and Software Engineering - System Life Cycle Processes]].''Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineers.[[ISO/IEC/IEEE 15288]]:2015.
  
 
===Additional References===
 
===Additional References===

Revision as of 15:47, 7 May 2015

System Maintenance planning begins early in the acquisition process with development of a maintenance concept. Maintenance planning is conducted to evolve and establish requirements and tasks to be accomplished for achieving, restoring, and maintaining operational capability for the life of the system. For a system to be sustained throughout its system life cycle, the maintenance process has to be executed concurrently with the operations process (ISO/IEC/IEEE 15288:2015, Clause 6.4.9).

Overview

The initial requirements for maintenance have to be defined during the stakeholder’s requirement definition process (Clause 6.4.1) (ISO/IEC/IEEE 15288:2015) and continue to evolve during the operation of the system. Considerations include

  • Maximizing system availability to meet the operational requirements. This has to take into account the designed-in reliability and maintainability of the system and resources available.
  • Preserving system operating potential through proper planning of system scheduled maintenance. This requires a reliability-centered maintenance strategy that incorporates preventive maintenance in order to preempt failures, thereby extending the mean time between corrective maintenance, as well as enhancing the availability of the system.
  • Segmentation of maintenance activities for potential outsourcing of non-critical activities to approved maintenance subcontractors as to optimize scarce technical manpower resources and maintenance/repair turn-around times.
  • Harnessing IT technology for maintenance management. This involves rigorous and systematic capturing and tracking of operating and maintenance activities to facilitate analysis and planning.

Maintenance management is concerned with the development and review of maintenance plans, as well as securing and coordinating resources, such as budget, service parts provisioning, and management of supporting tasks (e.g., contract administration, engineering support, and quality assurance). Maintenance planning relies on level of repair analysis (LORA) as a function of the system acquisition process. Initial planning addresses actions and support necessary to ensure a minimum life cycle cost (LCC).

Process Approaches

The purpose of the maintenance process is to sustain the capability of a system to provide a service. This process monitors the system’s capability to deliver services, records problems for analysis, takes corrective, adaptive, perfective, and preventive actions, and confirms restored capability. As a result of the successful implementation of the maintenance process

  • a maintenance strategy is developed
  • maintenance constraints are provided as inputs to requirements
  • replacement system elements are made available
  • services meeting stakeholder requirements are sustained
  • the need for corrective design changes is reported
  • failure and lifetime data is recorded

The project should implement the following activities and tasks in accordance with applicable organization policies and procedures with respect to the maintenance process:

  • scheduled servicing, such as daily inspection/checks, servicing, and cleaning
  • unscheduled servicing (carrying out fault detection and isolation to the faulty replaceable unit and replacement of the failed unit)
  • re-configuration of the system for different roles or functions
  • scheduled servicing (higher level scheduled servicing but below depot level)
  • unscheduled servicing (carrying out more complicated fault isolation to the faulty replaceable unit and replacement of the failed unit)
  • minor modifications
  • minor damage repairs
  • major scheduled servicing (e.g., overhaul and corrosion treatment)
  • major repairs (beyond normal removal and replacement tasks)

The maintenance plan specifies the scheduled servicing tasks and intervals (preventive maintenance) and the unscheduled servicing tasks (adaptive or corrective maintenance). Tasks in the maintenance plan are allocated to the various maintenance agencies. A maintenance allocation chart is developed to tag the maintenance tasks to the appropriate maintenance agencies. These include: in-service or in-house work centers, approved contractors, affiliated maintenance or repair facilities, original equipment manufacturer (OEMs), etc. The maintenance plan also establishes the requirements for the support resources.

Related activities such as resource planning, budgeting, performance monitoring, upgrades, longer term supportability, and sustenance also need to be managed. These activities are being planned, managed, and executed over a longer time horizon and they concern the well being of the system over the entire life cycle.

Proper maintenance of the system (including maintenance-free system designs) relies very much on the availability of support resources, such as support and test equipment (STE), technical data and documentation, personnel, spares, and facilities. These have to be factored in during the acquisition agreement process.

Training and Certification

Adequate training must be provided for the technical personnel maintaining the system. While initial training may have been provided during the deployment phase, additional personnel may need to be trained to cope with the increased number of systems being fielded, as well as to cater to staff turnover. Timely updates to training materials and trained personnel may be required as part of system upgrades and evolution. It is important to define the certification standards and contract for the training materials as part of the supply agreement.

Practical Considerations

The organization responsible for maintaining the system should have clear thresholds established to determine whether a change requested by end users, changes to correct latent defects, or changes required to fulfill the evolving mission are within the scope of a maintenance change or require a more formal project to step through the entire systems engineering life-cycle. Evaluation criteria to make such a decision could include cost, schedule, risk, or criticality characteristics.

References

Works Cited

ISO/IEC/IEEE. 2015.Systems and Software Engineering - System Life Cycle Processes.Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineers.ISO/IEC/IEEE 15288:2015.

Primary References

Blanchard, B.S. and W.J. Fabrycky. 2011. Systems Engineering and Analysis, 5th Edition. Upper Saddle River, NJ, USA: Prentice Hall.

DAU. 2010. Defense Acquisition Guidebook (DAG). Ft. Belvoir, VA, USA: Defense Acquisition University (DAU)/U.S. Department of Defense. February 19, 2010.

INCOSE. 2012. INCOSE Systems Engineering Handbook: A Guide for System Life Cycle Processes and Activities. Version 3.2.2. San Diego, CA, USA: International Council on Systems Engineering (INCOSE), INCOSE-TP-2003-002-03.2.2.

Institute of Engineers Singapore. 2009. Systems Engineering Body of Knowledge, Provisional version 2.0. Singapore: Institute of Engineers Singapore.

IISO/IEC/IEEE. 2015.Systems and Software Engineering - System Life Cycle Processes.Geneva, Switzerland: International Organization for Standardization (ISO)/International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineers.ISO/IEC/IEEE 15288:2015.

Additional References

None.


< Previous Article | Parent Article | Next Article >
SEBoK v. 1.9.1 released 30 September 2018

SEBoK Discussion

Please provide your comments and feedback on the SEBoK below. You will need to log in to DISQUS using an existing account (e.g. Yahoo, Google, Facebook, Twitter, etc.) or create a DISQUS account. Simply type your comment in the text field below and DISQUS will guide you through the login or registration steps. Feedback will be archived and used for future updates to the SEBoK. If you provided a comment that is no longer listed, that comment has been adjudicated. You can view adjudication for comments submitted prior to SEBoK v. 1.0 at SEBoK Review and Adjudication. Later comments are addressed and changes are summarized in the Letter from the Editor and Acknowledgements and Release History.

If you would like to provide edits on this article, recommend new content, or make comments on the SEBoK as a whole, please see the SEBoK Sandbox.

blog comments powered by Disqus