Systems Engineering and Project Management

From SEBoK
Jump to navigation Jump to search

The goal of project management is to plan and coordinate the work activities needed to deliver a satisfactory product, service, or enterprise endeavor within the constraints of schedule, budget, resources, infrastructure, and available staffing and technology. The purpose of this knowledge area (KA) is to acquaint systems engineers with the elements of project management and to explain the relationships between systems engineering and project management.

To download a PDF of all of Part 6 (including this knowledge area), please click here.

Topics

This knowledge area contains the following topics:

The Nature of Project Management

Project managers and systems engineers are both concerned with management issues such as planning, measuring and controlling, leading, directing, and managing risk. In the case of project managers, the project attributes to be managed include project plans, estimates, schedule, budget, project structure, staffing, resources, infrastructure and risk factors. Product attributes managed by systems engineers include items such as requirements allocation and flow-down, system architecture, structure of and interactions among technical teams, specialty engineering, integration , and verification and validation. The exact allocation of the SE and PM, duties depend on many factors such as customer and stakeholder interactions, organizational structure of the parent organization, and relationships with affiliate contractors and subcontractors. See the article on The Influence of Project Structure and Governance on Systems Engineering and Project Management Relationships in this KA.

The activities of project management include (Fairley 2009):

  • Planning and Estimating
  • Measuring and Controlling
  • Leading and Directing
  • Managing Risk

Planning and Estimating

Planning a project involves providing answers to the who, what, where, when, and why questions.

  • Who: addresses staffing issues (competencies, numbers of staff, communication and coordination)
  • What: addresses the scope of activities
  • Where: addresses issues of locale (local, geographically distributed)
  • When: addresses scheduling issues
  • Why: addresses rationale for conducting a project

Guidance for developing project plans can be found in (INCOSE 2011), (NASA 2007), and (ISO/IEC/IEEE Standard 16326:2009). It is often observed that communication and coordination among stakeholders during project planning are equally important and sometimes more important than the documented plan that is produced.

Estimation is an important element of planning. An estimate is a projection from past to future, adjusted to account for differences between past and future. Estimation techniques include analogy, rule of thumb, expert judgment, and use of parametric models such as COCOMO for software projects and COSYSMO for systems projects (Boehm et al 2000, Valerdi 2008).

Systems engineering contributes to project estimation by ensuring that:

  • the overall system life cycle is understood
  • dependencies on other systems and organizations are identified
  • the logical dependencies during development are identified
  • resources and key skills are identified and planned

Additionally, the high-level system architecture and a risk assessment provide the basis for the work breakdown structure and the organizational breakdown structure.

Measuring and Controlling

Measuring and controlling are the key elements of executing a project. Measurement includes collecting measures for work products and work processes. For example, determining the level of coverage of requirements in a design specification can be assessed by reviews, analysis, prototyping, and traceability. Effort and schedule expended on the work processes can be measured and compared to estimates; earned value tracking can be used for this purpose. Controlling is concerned with analyzing measurement data and implementing corrective actions when actual status does not align with planned status. Additional information on measurement and control of technical factors can be found in the Measurement and Assessment and Control articles in Part 3 of this SEBoK.

Leading and Directing

Leading and directing requires communication and coordination among all project stakeholders, both internal and external to a project. Systems engineers may be responsible for managing all technical aspects of project execution, or they may serve as staff support for the project manager or project management office. Organizational relationships between systems engineers and project managers are presented in Organizing Teams to Perform Systems Engineering in Part 5 of this SEBoK. Other organizational considerations for the relationships between systems engineering and project management are covered in Part 5, Enabling Systems Engineering.

Managing Risk

risk management is concerned with identifying and mitigating potential problems before they become real problems. Systems engineering projects are, by nature, high-risk endeavors because of the many unknowns and uncertainties that are inherent in projects. Because new risk factors typically emerge during a project, ongoing, continuous risk management is an important activity for both systems engineers and project managers.

Every aspect of a project may encounter potential and real problems; systems engineers are typically concerned with technical risk and project managers with programmatic risk. Sometimes, technical risk factors are identified and confronted by systems engineers and programmatic risk factors are identified and confronted by project managers, but without adequate communication between them. In these cases appropriate tradeoffs among requirements, schedule, budget, infrastructure, and technology may not be made, which creates additional risk for the successful outcome of a project.

Additional information on risk management for systems engineering projects can be found in the Risk Management article in Part 3 of this SEBoK.

References

Works Cited

Boehm, B., C. Abts., A.W. Brown, S. Chulani, B.K. Clark, E. Horowitz, R. Madachy, D. Reifer, and B. Steece. 2000. Software Cost Estimation with COCOMO II. Upper Saddle River, NJ, USA: Prentice Hall.

Fairley, R.E. 2009. Managing and Leading Software Projects. Hoboken NJ, USA: John Wiley & Sons.

INCOSE. 2011. Systems Engineering Handbook: A Guide for System Life Cycle Processes and Activities, version 3.2.1. San Diego, CA, USA: International Council on Systems Engineering (INCOSE), INCOSE-TP-2003-002-03.2.1.

ISO/IEC/IEEE. 2009. Systems and Software Engineering - Life Cycle Processes - Project Management. Geneva, Switzerland: International Organization for Standardization (ISO)/International Electronical Commission (IEC)/Institute of Electrical and Electronics Engineers (IEEE), ISO/IEC/IEEE 16326:2009(E).

NASA. 2007. Systems Engineering Handbook." Washington, DC: National Aeronautics and Space Administration.

Valerdi, R. 2008.The Constructive Systems Engineering Cost Model (COSYSMO): Quantifying the Costs of Systems Engineering Effort. Saarbrucken, Germany: VDM Verlag.

Primary References

Fairley, R.E. 2009. Managing and Leading Software Projects. Hoboken, NJ, USA: John Wiley & Sons.

PMI. 2008. A Guide to the Project Management Body of Knowledge, 4th ed. Newtown Square, PA, USA: Project Management Institute (PMI).

Additional References

Blanchard, B. 2008. System Engineering Management. Hoboken, NJ, USA: John Wiley & Sons.

Martin, J. 1997. Systems Engineering Guidebook: A Process for Developing Systems and Products. London, UK: Taylor and Francis Group CRC-Press, LLC.


< Previous Article | Parent Article | Next Article >

Comments from SEBok 0.5 Wiki

No comments were logged for this article in the SEBoK 0.5 wiki. Because of this, it is especially important for reviewers to provide feedback on this article. Please see the discussion prompts below.

SEBoK v. 1.9.1 released 30 September 2018

SEBoK Discussion

Please provide your comments and feedback on the SEBoK below. You will need to log in to DISQUS using an existing account (e.g. Yahoo, Google, Facebook, Twitter, etc.) or create a DISQUS account. Simply type your comment in the text field below and DISQUS will guide you through the login or registration steps. Feedback will be archived and used for future updates to the SEBoK. If you provided a comment that is no longer listed, that comment has been adjudicated. You can view adjudication for comments submitted prior to SEBoK v. 1.0 at SEBoK Review and Adjudication. Later comments are addressed and changes are summarized in the Letter from the Editor and Acknowledgements and Release History.

If you would like to provide edits on this article, recommend new content, or make comments on the SEBoK as a whole, please see the SEBoK Sandbox.

blog comments powered by Disqus