Difference between revisions of "Issue (glossary)"

From SEBoK
Jump to navigation Jump to search
m (Text replacement - "<center>'''SEBoK v. 1.9.1, released 16 October 2018'''</center>" to "<center>'''SEBoK v. 2.0, released 1 June 2019'''</center>")
m (Text replacement - "<center>'''SEBoK v. 2.0, released 1 June 2019'''</center>" to "<center>'''SEBoK v. 2.1, released 31 October 2019'''</center>")
Line 13: Line 13:
 
[[Category:Glossary of Terms]]
 
[[Category:Glossary of Terms]]
  
<center>'''SEBoK v. 2.0, released 1 June 2019'''</center>
+
<center>'''SEBoK v. 2.1, released 31 October 2019'''</center>

Revision as of 13:31, 24 October 2019

(1) An area of concern that may impact the achievement of program/organizational objectives – a problem (existing), a risk (future uncertainty), or lack of information (existing). (PSM 2010)

(2) A concern that has a probability of occurrence equal to one, a consequence of occurrence greater than zero, and a time-frame in the future. An issue will occur and have a negative impact to the project, but it will not immediately occur. (Conrow 2008)

Source

(1) PSM. 2010. Practical Software and Systems Measurement: A Foundation for Objective Project Management, version 4.0. Bethesda, MD, USA: Practical Software and Systems Measurement.

(2) Conrow, E. 2008. "Risk Analysis for Space Systems." Space Systems Engineering and Risk Management Symposium, 27-29 February, 2008, Los Angeles, CA, USA.

Discussion

Definition (2) defines issue in terms of probablity of occurrence, consequence of occurrence, and time-frame; all of which are measurable.