Figure 1. Subsystems of the SKLTS (Ahn, 2005) (''Notes'': CCU: Central Control Unit; TTC: Total Traffic Control; ATP: Automatic Train Protection; ATO: Automatic Train Operation; PSD: Platform Screen Door)
 
Figure 1. Subsystems of the SKLTS (Ahn, 2005) (''Notes'': CCU: Central Control Unit; TTC: Total Traffic Control; ATP: Automatic Train Protection; ATO: Automatic Train Operation; PSD: Platform Screen Door)
  
The [[Life Cycle Models|project life cycle]] for the SKLTS is summarized in Figure 2. It consists of 7 phases: concept studies, concept development, preliminary design, design, system production and test, performance evaluation, and operation/maintenance/close-out (OMC) see Choi (2007) and Chung et al. (2010) for details. Each phase except the production and test phase is complete with the evaluation and decision point (EDP), which is depicted as a colored circle in the figure.
+
The [[Life Cycle Models|project life cycle]] for the SKLTS is summarized in Figure 2. It consisted of 7 phases: concept studies, concept development, preliminary design, design, system production and testing, performance evaluation, and operation/maintenance/close-out [[Acronyms|(OMC)]] - please see Choi (2007) and Chung et al. (2010) for further details. Each phase except the production and test phases are complete with the evaluation and decision point (EDP), which is depicted as a colored circle in the figure.
  
 
[[File:ChoeKimFigure2.png|600px|System Engineering Processes for the URTS]]
 
[[File:ChoeKimFigure2.png|600px|System Engineering Processes for the URTS]]

Revision as of 18:09, 1 September 2011

In order to illustrate concepts described in the Systems Engineering Body of Knowledge (SEBoK), this vignette deals with systems engineering (se) concepts and guidelines applied to the development of the Standard Korean Light Transit System (SKLTS). The system itself is not for commercial operation, but for providing a reliable technical platform for planned commercial systems.

In Korea, local authorities have been interested in light transit to help resolve their transportation problems. They, along with the central government, decided to develop the standard platform of Korean light transit systems during the 7-year period between 1999 and 2005. After completion, local authorities introduced the SKLTS to their precincts. Successful examples include the Inchun Airport Line and the Seoul 9th Subway Line.

Design of the transit system was developed with the emphasis on reliability, availability, maintainability, and safety [[Acronyms|(RAMS)). The project organization consisted of representatives from various institutions, including the central government, local authorities, and companies involved. The objective of the project was the verification and validation [[Acronyms|(V&V)) of the SKLTS using a test railway.

Following the guidance of ISO/IEC/IEEE 15288, the project lifecycle of the SKLTS was designed with seven phases from concept studies to operation. (Korea Technology and Standard Institute 2009) In each phase, the project identified issues related to RAMS. Requirement analysis identified RAMS issues of various stakeholders. Functional analysis and allocation were based on scenario-based simulations that utilized SE tools such as RDD-100 (a requirements management tool). The SE activities of the project were designed to ensure that the whole system would achieve desired RAMS level.

Vignette Description

The SKLTS provides the standard platform on which any local authority can construct its light transit system. Hence, its design had to accommodate many various requirements not only from local authorities but also the central government. The project schedule was as follows:

  • 1999: concept studies and development
  • 2000: pre-design
  • 2001: design
  • 2002-2004: production and testing
  • 2005: performance evaluation
  • 2006 and later : subsequent proliferation

The elements of the SKLTS can be classified into 4 groups (as shown in Figure 1): trains, signal systems, electric and machinery (E&M) systems, and structures. Trains and vehicles are intended to be automatically operated, without need for human operators. Operation systems and their interfaces are based on digital signals and communications. For SKLTS, SE-based design activities focused on RAMS, and were be integrated into project management activities during all phases.

Elements of the Unmanned Light Transit System

Figure 1. Subsystems of the SKLTS (Ahn, 2005) (Notes: CCU: Central Control Unit; TTC: Total Traffic Control; ATP: Automatic Train Protection; ATO: Automatic Train Operation; PSD: Platform Screen Door)

The project life cycle for the SKLTS is summarized in Figure 2. It consisted of 7 phases: concept studies, concept development, preliminary design, design, system production and testing, performance evaluation, and operation/maintenance/close-out (OMC) - please see Choi (2007) and Chung et al. (2010) for further details. Each phase except the production and test phases are complete with the evaluation and decision point (EDP), which is depicted as a colored circle in the figure.

System Engineering Processes for the URTS

Figure 2. 7 phases of the SKLTS development

The phase of concept studies is to identify possible stakeholders and their preliminary requirements, and to research the current status of technologies required. The EDP at the end of this phase is based on user requirement documents and concept study reports. Experts outside the project team also participate in the review process.

The phase of concept development is to determine stakeholders and their requirements in a more systematic and comprehensive way. The major outputs include complete requirements documents and reports.

The major objective of the preliminary design phase is to provide the request for proposal (RFP), which emphasizes SE implementation. If the system is required to be divided into several subsystems, their interrelationships and interfaces are examined during this phase. Then an RFP is provided for each subsystem.

The design phase begins with establishing the baseline. Every user requirements should be met by design. This correspondence is managed during the whole lifecycle. At the EDP, the results of this phase are evaluated by pre-design reports, requirement analysis documents, project baseline, and final design.

The phase of system production and test consists of system development, production, test, and operation training. This phase does not have any formal EDP, which is scheduled at the end of the performance evaluation phase. Instead, various check points are scheduled during production and test processes.

The performance evaluation phase focuses on the validation of user requirements and the verification of design. The validation process is based on requirements documents, baseline plans, and V&V results of system elements. This phase also includes activities to prepare commercial operation. Activities of the OMC phase are supported by the results of previous phases. The third-party evaluation team will monitor them.

SE Framework of the SKLTS

SE activities during the SKLTS development focus on RAMS as summarized in Tab. 1. In the phases for concept studies and concept development, SE activities identify all the requirements for the system to define the target performance including the objectives of reliability, availability, and maintainability (RAM). Design criteria and system functions are also established. Planning activities in this phase include various tests and evaluations scheduled in the future. The basic layout of rails and command rooms is proposed. Finally, we define interface management procedures and relationships between requirements and systems. For RAMS engineering, we also establish various plans and criteria such as RAM plans, safety plans, service availability, and so on.

The SE Framework of the SKLTS

Table 1. The SE framework of the SKLTS (Ahn, 2005)

In the pre-design phase, the basic architecture of the system is determined for safety planning, RAM planning, and operation scenarios. Interfaces among subsystems are carefully defined as well as management procedures for contractors and legal regulations. The function analysis deals with timeline, accuracy of stop points and trip times. Pre-design activities include the specifications of major system elements such as signal systems, trains, interface and so on. For RAMS engineering, safety scenarios are defined, and the hazard and risk analysis is performed.

During the phases for design and performance evaluation, the hazard log and RAM analysis are performed to meet safety requirements for every subsystems. The specifications of alarm systems and stations are also defined. V&V procedures are determined for performance evaluation. Then the testing team is established to specify test procedures.

Initial operation is performed only after the system is accepted and operators are properly certified. During test operation, RAM performance is continuously monitored. The FRACAS is operated to gather accident and failure data. Its results will help the maintenance system and procedures. Continuous improvement is required when the system is in normal operation.

Project Organization

The project organization of the SKLTS is shown in Fig. 3. The Ministry of Construction and Transportation is the major sponsor, and the Korea Railroad Research Institute (KRRI) is responsible for project management. The steering committee consists of representatives of the ministry, research institutions, project members, and audit agency. According to the classification scheme shown in Fig. 1, the project organization consists of 5 parts such as engineering, train systems, power supply systems, signal & control systems, and structures. Each part has main contractors shown in the parentheses, and consists of 3 ~ 12 companies.

SKLTS Project Organization

Figure 3. SKLTS project organization (Han, 2006)

Requirements Analysis

Requirements of the SKLTS are classified into mission requirements and system requirements by using an SE tool, RDD-100. Mission requirements can be summarized as follows:

  • To have the transportation capability of 5,000~20,000 passengers/one way
  • To be based on existing urban railway systems and technologies
  • To evaluate performance by test railway
  • To effectively apply SE principles and guidelines
  • To provide LR service safer than legacy rail services
  • To be efficient under the domestic environment

These requirements are defined in the first phase. In the following phases, they are refined especially with the consideration of environment, function, safety, v&v, regulations, and technologies. System requirements are classified into 4 groups as follows:

  • I/O requirements: system input, system output, external interface, function
  • Technology requirements: technology, “-ilities”, cost, time
  • Trade-off requirements: cost, performance, cost vs. performance
  • V&V requirements: v&v, certification

Function Analysis and Allocation

For the function analysis, RDD-100 provides a scenario-based simulation module called as DVF (Dynamic Verification Facility). It is able to run scenario-based simulation so that the precedence relationships of functions and messages among them can be identified. In other words, we use scenarios to evaluate the dynamic behavior of the system. For example, the functions of trains are simulated by scenarios as follows:

  • Pre-test scenario
  • Normal operation scenario
  • Emergency operation scenario
  • Rescue operation scenario

A scenario example of the lowest level by RDD-100 is given in Fig. 4. Using the results of the function analysis, functions are allocated to the elements in the systems architecture (Lee, 2002). Fig. 5 shows an example of function and requirement allocation.

Scenario for self inspection

Figure 4. An example of behavior scenarios by RDD-100 (Han and Lee, 2005)

Function and requirement allocation

Figure 5. An example of function and requirement allocation (Han and Lee, 2005)

Design

For integrated and consistent design, the design/construction interface manual (D/CIM) is defined, and applied to every details of design (Bombardier, 2005). The D/CIM specifies the detail of trains, railway, and structures.

Verification and Validation

The safety and reliability of the SKLTS are evaluated on test railway which is constructed by the standard specifications. These issues are very critical to the success of the SKLTS, because it is an automatically-driven system. In addition to our own data, experiences and data in countries with unmanned LTS are very helpful for tests and specifications related to safety and reliability. For ensuring safety, the safe operation guidelines are enforced. The guidelines show how to recover and operate the system under each type of accidents and emergencies.

Specialty Engineering - RAMS

RAMS is one of major interest. Hence, various methods are applied for achieving the RAMS objectives. Some of them are the RAMS requirements analysis, safety and RAMS planning, systems scenarios, construction risk analysis, and RAMS analysis reports.

First, for the comprehensive RAMS requirements analysis, every quantitative and qualitative requirement for RAMS is identified. Examples are as follows;

  • Target level of reliability and availability
  • Requirements analysis for subsystems to ensure those of the whole system
  • Tolerance limits of reliability tests
  • Engineering guidelines for the maintainability of the system
  • Safety criteria
  • Risk limits of the system including passengers, operators, etc.
  • Allocation of the safety level of each subsystem
  • Guidelines for accidents and emergencies

Both qualitative and quantitative requirements for safety are defined. Those requirements are analyzed not only for the railway system but also for facilities and structures, such as ATC, SCADA, command rooms, platform sliding doors, and so on. The requirements analysis for safety leads to the safety plan. It defines safety-related works and processes of each phase, and also the safety management organization. It also includes the safety plans of contractors. Managing factors related to RAM, the RAM plan defines activities and procedures necessary in each phase of the lifecycle. The plan is revised with the results and schedules of phases.

System scenarios are important documents for evaluating the functions required for unmanned operation. For making scenarios, we assume the 3 types of operation modes (normal operation, fall-back operation, and emergency operation) and the 2 types of facilities (stations and depots). Hence 6 scenarios are evaluated in the end. Each scenario describes actions, procedures, timelines, and signals necessary for the situation.

The construction risk analysis specifically focuses on construction and civil works. Risk factors of construction are identified from the early phase, and their list is properly maintained. For example, the analysis is re-checked whenever an engineering change is required. Each risk identified is resolved and managed by engineering design teams. The analysis also suggests the roles and responsibilities of risk management personnel and the schedules of activities required.

The RAM analysis report shows if the whole system may achieve the desired RAM level by analyzing RAM data of subsystems. First, the RAM factors of each subsystem are identified, and their effects on the whole system are evaluated. Proper actions are taken to resolve an issue, if required. Second, each subsystem is verified to achieve the reliability objectives desired. Finally, the cost and time for overall RAM actives are estimated.

Summary

This case deals with systems engineering (SE) concepts and guidelines applied for the development project of the standard Korean light transit system (SKLTS). In Korea, local authorities have been interested in light transit systems to resolve their transportation problems. They with the central government developed the standard type of Korean light railway systems during the 7-year period between 1999 and 2005. Then local authorities introduced the SKLTS to their precincts with some modifications. Successful examples include the Inchun Airport Line and the Seoul 9th Subway Line.

The SKLTS is initiated to provide its flexible basis. Hence, in addition to the typical design of the railway system, we need to focus on reliability, availability, maintainability, and safety (RAMS) with comprehensive level and interface management. The project organization consists of representatives from various institutions including the central government, local authorities, and companies involved.

SE works and activities are supported by an SE tool, RDD-100. It is capable of scenario-base simulation for the function analysis. Design activities are integrated mostly by the use of the design/construction interface manual (D/CIM). We apply various methods to achieve the objectives related to RAMS. Some of them are the RAMS requirements analysis, safety and RAMS planning, systems scenarios, construction risk analysis, and RAMS analysis reports. These methods enable us to effectively manage project activities, and to achieve the objective desired.

It was found that the SE tool itself is not critical to the success of the project, and that the requirement analysis especially in the first few phases should be more complete. Finally, this article does not have the details of SE activities for interface management, configuration management, EMI/EMC management, and noise/vibration management.

References

Citations

  • Ahn, S. H., “Systems engineering applied to the construction of unmanned light rail transit systems”, Journal of the Korean Society for Railway, Vol. 8, No. 2, pp. 41-49, 2005.
  • Bombardier, Design/Construction Interface Manual, 2005.
  • Choi, Y. C., Systems Engineering Application Model for the National R&D Project: Focusing on the Railway Systems, Ph.D. dissertation, Ajou Univ., 2007.
  • Chung, S. Y., Lee, S. G., Lee, D. W. and Jeon, S. T., “A study on the application model of systems engineering to advance the business of the Light Rail Transit (LRT)”, Proceedings on the Autumn Conference of the Korean Society for Railway, pp. 24-30. 2010.
  • Han, S. Y. and Lee, A. H., System Engineering for the Technology Development Program of Light Transit Systems, internal research report, the Korea Railroad Research Institute, 2005.
  • Korea Technology and Standard Institute, KSX ISO/IEC 15288: Life Cycle Processes of IT Systems Based on Systems and Software Engineering, research report, The Korea Technology and Standard Institute, 2009.
  • Lee, W. D., “A study on the top-level functional analysis for the automated guideway transit by system engineering tools”, Proceedings on Autumn Conference of the Korean Society for Railway, pp. 202-207, 2002.

Primary References

None.

Additional References

None.


Article Discussion

[Go to discussion page]

<- Previous Article | Parent Article | Last Page (Return to Home)

5 Usage quibble: "7-year period between 1999 and 2005" -- the period BETWEEN 1999 and 2005 would be 2000, 2001, 2002, 2003 and 2004 -- or 5 years. The 7-year period is the "period of 1999 to 2005".

Figure 1 does not seem to show up as a figure.

"integrated TO project management activities" should, I think, be "integrated WITH project management activies".

"The project lifecycle for the SKLTS is summarized as Figure 2." WHERE is Figure 2?

"Figure 2. also does not appear as a figure.

"Every user requirements should be met by design..." "requirement" should be singular.

There are references within the body to "Tab 1" and "Table 1". WHERE are these? It appears that the entire paragraph following the words "Table 1" was supposed to be in table form. But it isn't -- all the words are run together as though it was regular prose.

Figure 3 missing as well. Appears to be a formatting issue with figures and tables. ALL FIGURES seem missing or somehow not formatted.

Descriptive: OK

balance: OK

Scope: OK

Writing: Some issues -- apparently it is largely formatting for the WIKI that is the problem.

Citations: OK

References: OK

Glossary: OK

Cross-Linkages: OK

Maturity: Good, except for formatting issues with figures, tables.

(Davidz, 08/22) New text from Dr. Choe entered today, tried to correct first person references, updated hyperlinks, still need figures and tables

Signatures

--Hdavidz 15:05, 15 August 2011 (UTC)